The short answer
A wind mitigation inspection is a short visit in which a qualified inspector documents the parts of your home that help it resist hurricane winds: the roof covering, how the roof deck is nailed, how the roof is tied to the walls, the shape of the roof and the protection on every window and door. The findings go on Florida's official form, OIR-B1-1802, and your insurance company uses that form to decide which windstorm credits apply to your policy.
Key points
- It is optional. Florida law requires insurers to offer windstorm credits, but no law requires you to get the inspection.
- There is no pass or fail. The inspector records what your house has, and your insurer decides what it is worth.
- Inspections on or after April 1, 2026 use the revised form, Rev. 04/26, which asks nine questions instead of seven.
- The form is valid for up to five years, as long as the structure does not change and nothing on it turns out to be inaccurate.
- Most visits take under an hour, and the signed form usually arrives the same day.
In this article 14 sections
- What is a wind mitigation inspection?
- Why Florida has this inspection, and why your insurer cares
- What changed with the 2026 form
- The 9 items on the form, one by one
- What happens during the visit, step by step
- How to prepare for a wind mitigation inspection
- The weakest-link rule, and what "unknown" really means
- South Florida: why the same house can answer differently
- Upgrades that can change your answers
- Wind mitigation vs. 4-point vs. full home inspection
- How much does a wind mitigation inspection cost?
- Six common misunderstandings
- Who can sign a wind mitigation form
- The bottom line
What is a wind mitigation inspection?
"Mitigation" simply means reducing damage. In Florida, a wind mitigation inspection is the visit that proves which damage-reducing features a home already has. An inspector looks at the roof, goes into the attic, walks around every opening, checks the permit history and records the answers on the Uniform Mitigation Verification Inspection Form, better known by its number, OIR-B1-1802. Each answer has to be backed by a photo or a document.
You will hear it called a wind mit, a windstorm mitigation inspection, a hurricane mitigation inspection or simply a wind inspection. They are all the same visit and the same form. Whether you searched for "what is a windstorm mitigation inspection" or "what does a wind mitigation inspection entail", this is the inspection people mean.
It helps to know what it is not. It is not a full home inspection, so it will not tell you whether the A/C works or the roof leaks. It is not an engineering certification either: the form itself ends by saying its definitions are "for inspection purposes only and cannot be used to certify any product or construction feature as offering protection from hurricanes." And it is not something a house passes or fails. The inspector reports what is there. What that is worth on your premium is your insurer's decision.
Why Florida has this inspection, and why your insurer cares
Florida's insurance code ties the inspection to your premium. Section 627.0629 of the Florida Statutes says a residential property insurance rate filing "must include actuarially reasonable discounts, credits, or other rate differentials, or appropriate reductions in deductibles" for homes with construction features shown to reduce windstorm losses. Section 627.711 then requires insurers to tell applicants and policyholders about those discounts when a policy is issued and at every renewal, and it created one uniform form that every insurer has to accept from a qualified inspector. That form is the wind mitigation report.
In practice, the inspection is how a feature becomes a credit. Your insurer cannot credit hurricane straps it has no record of. The form is that record, and it tells the insurer, item by item, how your house was built and what has been added since.
Two limits are worth understanding before you book. First, wind mitigation credits apply to the windstorm portion of your premium, not to every part of the policy. Second, the amounts belong to each insurer. They come from rate filings, they differ from company to company, and every page of the form carries the warning that "some items listed may not qualify for a discount." Since October 1, 2023, insurers have also had to describe their hurricane mitigation discounts on their own websites, which is a good place to look before you call your agent.
Is a wind mitigation inspection required in Florida?
No. There is no state law that makes you get one, and no inspector or agent can make it mandatory. It is a voluntary inspection that exists for your benefit. That said, without the form your insurer has nothing on file to credit, so skipping it usually means paying as if your home had none of the features it may actually have.
It tends to pay off in these situations:
- You are buying a home. Order it before you bind insurance, so the quote reflects the house you are actually buying. If the seller has a recent report, ask for it.
- Your renewal is coming up and you have never had one, or your last report is close to five years old.
- You improved the house. A new roof, impact windows, shutters or a rated garage door only count once they are documented.
- Your home is newer. Permit dates and product approvals are usually easy to find, which makes several items straightforward to document. On a brand-new house, it can be done at the final visit before closing, as our guide to inspecting a brand-new Florida home explains.
- Your home is older. Houses built long before today's codes can still earn credits for a hip roof, straps added later or protected openings.
What changed with the 2026 form
Florida's Office of Insurance Regulation revised the form, and the new version, OIR-B1-1802 (Rev. 04/26), adopted by Rule 69O-170.0155 of the Florida Administrative Code, must be used for inspections conducted on or after April 1, 2026. The version it replaced dated from January 2012 and asked seven questions. The new one asks nine, and several of the old answers now have more options.
| Topic | 2012 form (Rev. 01/12) | 2026 form (Rev. 04/26) |
|---|---|---|
| Number of items | 7 | 9 |
| Building code | FBC 2001 or later, or SFBC-94 in the HVHZ | Separates FBC 2001 and 2004 from FBC 2007 or later, based on the code in force when the permit was applied for |
| Region | Not asked | New item 2: HVHZ, Region 1, 2 or 3, by design wind speed |
| Roof slope | Not asked | New item 3: 6:12 or steeper, or flatter |
| Roof covering | Shingle, tile, metal, built-up, membrane, other | Adds synthetic or composite tile |
| Roof deck attachment | A to D, other, unknown, no attic access | Adds spray foam with a 110 psf uplift resistance |
| Roof to wall attachment | Toe nails, clips, single wraps, double wraps, structural | Adds tested retrofit connectors and "connections not installed as intended" |
| Secondary water resistance | Sealed roof deck, yes or no | Spells out four accepted methods |
| Opening protection | A, B, C, N or X | Adds Z for damaged openings |
| FORTIFIED certificates | Not listed | Roof, Silver and Gold certificates can validate items 4 to 6 and 8 to 9 |
If you already have a report on the 2012 form, it is not automatically worthless. Citizens Property Insurance said it will keep accepting the previous version if it was completed within five years before April 1, 2026 and no changes have been made to the structure, and that the new features will not change the credits it offers at this time. Other insurers set their own rules, so ask your agent before assuming an older report still works. If the house has changed since the last report, or the report is close to five years old, a new inspection on the current form is the cleaner path.
The 9 items on the form, one by one
The form follows the path wind takes through a house: where the home is and which code it was built under, then the roof covering, the deck under it, the connection between roof and walls, the shape of the roof, the water barrier under the covering and finally the openings. Every attribute marked in items 2 through 9 needs at least one photograph or document attached as proof.
Three of the nine items ask for the weakest example on the house, not the typical one: roof deck attachment, roof-to-wall attachment and opening protection. Keep that in mind as you read, because it explains most of the surprises people have when they get their report.
| # | Item | What it asks | Verified from |
|---|---|---|---|
| 1 | Building Code | Which code was in force when the permit was applied for | Permit records |
| 2 | Region | The design wind speed at your address | ASCE 7-22 hazard tool |
| 3 | Roof Slope | Is the main roof 6:12 or steeper | Measured on site |
| 4 | Roof Covering | Is every roof covering documented as code-approved | Roof, permits, product approvals |
| 5 | Roof Deck Attachment | How the roof sheathing is fastened, at its weakest | Attic |
| 6 | Roof to Wall Attachment | How the roof is tied to the walls, at its weakest | Attic |
| 7 | Roof Geometry | Hip, flat or other | Perimeter measurements |
| 8 | Sealed Roof Deck / SWR | Is there a second water barrier under the covering | Attic, roofing documents |
| 9 | Opening Protection | How every window, door and skylight is protected, at its weakest | Every opening, labels, approvals |
Item01
Building Code
This item asks which code was in force when the home's building permit application was filed. The answers are the Florida Building Code 2001 and 2004, the FBC 2007 or later, and, only inside the High-Velocity Hurricane Zone of Miami-Dade and Broward, the 1994 South Florida Building Code (SFBC-94). If none of them can be shown, the answer is unknown.
The year the house was finished is not always enough. The form asks for a permit application dated after March 1, 2002 for homes built in 2002 or 2003, after December 8, 2006 for homes built in 2007 or 2008, and, in the HVHZ, after September 1, 1994 for homes built from 1994 to 1996. A house completed in 2002 on a permit filed in 2001 was built under the rules that came before the Florida Building Code, which took effect on March 1, 2002.
- Where we look
- City or county permit records for the address
- Have ready
- The original building permit or its application date, if you have it
Item02
Region
New in 2026. The answer comes from the design wind speed at your address in the ASCE 7-22 hazard tool: HVHZ, Region 1 (140 mph or more), Region 2 (130 to 139 mph) or Region 3 (below 130 mph). Every address in Miami-Dade and Broward answers HVHZ. In Palm Beach County, which sits outside the HVHZ, the region is looked up for each address instead of being assumed for a whole city.
- Where we look
- The ASCE hazard tool, by address
- Have ready
- Nothing. This one is on us
Item03
Roof Slope
Also new. It records whether the main roof is 6:12 or steeper, which means it rises at least 6 inches for every 12 inches it runs horizontally, or flatter than that. When a single-family home has several slopes, the answer follows the slope that covers at least two-thirds of the main roof area, so a low-slope porch or addition does not decide it on its own.
- Where we look
- The roof itself, measured on site and photographed
- Have ready
- Nothing
Item04
Roof Covering
The inspector lists every covering on the house: asphalt or fiberglass shingle, concrete or clay tile, synthetic or composite tile, metal, built-up, membrane or something else. For each one, the form wants a permit application date or a Florida or Miami-Dade product approval number, plus the year it was installed or replaced, or a note that no information was available.
The overall answer is A when every covering meets the Florida Building Code: a product approval current at installation, a roofing permit applied for on or after March 1, 2002, or an original roof on a home built in 2004 or later. B covers Miami-Dade product approvals and, in the HVHZ only, roofing permits applied for between September 1, 1994 and March 1, 2002, or an original roof built in 1997 or later. If one covering falls short, the answer drops to C. If none qualify, it is D. That is why a small flat roof over a Florida room, added without a permit, deserves attention: it can pull the whole item down.
- Where we look
- The roof, plus permit records and product approvals
- Have ready
- Re-roof permit, roofing contract or invoice showing the product approval numbers
Item05
Roof Deck Attachment
This item looks at how the plywood or OSB sheathing under your roof covering is fastened to the trusses or rafters, and it is graded at its weakest point. For sheathing at least 7/16 inch thick on framing spaced no more than 24 inches apart, the main answers depend on nail size and spacing:
- A: staples or 6d nails spaced 6 inches along the edges and 12 inches in the field, or any system with a mean uplift resistance of at least 55 psf.
- B: 8d common nails spaced no more than 12 inches in the field, or an equivalent of at least 103 psf.
- C: 8d common nails spaced no more than 6 inches in the field, or an equivalent of at least 182 psf. Dimensional lumber or tongue-and-groove decking with at least two nails per board (one if each board is 6 inches wide or less) also answers C.
- D: a reinforced concrete roof deck.
- E: new in 2026, spray foam with an uplift resistance of 110 psf, installed along the rafter and deck intersections and every panel joint.
- Other, unknown or unidentified, or no attic access.
Most of this is verified from the attic, where the inspector measures and photographs the nail spacing along the framing with a tape measure in the shot. If the attic hatch is sealed, blocked or missing, items 5 and 6 cannot be verified at all.
- Where we look
- The underside of the roof deck, from the attic
- Have ready
- A clear path to the attic hatch

Item06
Roof to Wall Attachment
Here the question is how the roof framing is anchored to the walls, again graded by the weakest connection. Hip and valley jack trusses within five feet of an inside or outside corner of the roof are not counted when choosing the weakest. From weakest to strongest, the answers are:
- Toe nails: trusses nailed at an angle into the top plate of the wall, or metal connectors that do not meet the conditions for the categories above them.
- Clips: metal connectors that do not wrap over the top of the truss or rafter.
- Single wraps: one strap that wraps over the truss, with at least two nails on the front side and one on the opposite side.
- Double wraps: two straps, one on each side of the truss, each wrapping over the top, or a single wrapping strap secured to the wall on both sides with at least three nails on each side.
- Structural: anchor bolts structurally connected, or a reinforced concrete roof.
- Other, unknown, no attic access, or connections not installed as intended.
Clips and wraps only count when they meet the form's minimum conditions: at least three nails into the truss, attached to the top plate or embedded in the bond beam, less than half an inch from the truss or blocking, blocked no more than an inch and a half from it, and free of visible severe corrosion. That last condition matters near the coast, where salt air works on metal for decades.
The 2026 form also recognizes tested retrofit connectors. A purpose-made connector installed to the manufacturer's specifications can qualify by its documented uplift capacity: 386 pounds or more for clips, 535 for single wraps and 891 for double wraps, with site-specific documentation.
- Where we look
- The top of the walls, from the attic, along the whole perimeter we can reach
- Have ready
- Paperwork from any strap or connector retrofit

Item07
Roof Geometry
A hip roof slopes down on every side, which helps it shed wind. On the form, a roof counts as hip when other roof shapes make up no more than 10% of the total roof system perimeter, and the inspector writes both measurements on the form. A flat roof applies to buildings with five or more units where at least 90% of the main roof area has a slope under 2:12. Everything else is "other". Porch and carport roofs attached only to the fascia or wall over unenclosed space are left out of the calculation.
This is a measurement, not an impression from the street. A house that looks hip from the front can have a gable over the garage or a rear addition that pushes it over the 10% line, and a house that looks complicated can still qualify once the perimeter is measured.
- Where we look
- The roof perimeter, measured around the house and photographed
- Have ready
- Nothing

Item08
Sealed Roof Deck / Secondary Water Resistance (SWR)
SWR is a second line of defense under the roof covering. If wind strips shingles or tiles away, it keeps water from pouring through the deck. The form is explicit that standard underlayment and hot-mopped felt do not qualify. The accepted methods are a fully adhered polymer-modified bitumen underlayment meeting ASTM D1970, deck seams covered with a self-adhering strip at least 3.75 inches wide under felt or synthetic underlayment, two layers of listed felt or synthetic underlayment without tape, or spray foam applied along the rafter and deck intersections and panel joints.
On a finished roof, SWR is rarely visible from above. The inspector looks for it from the attic side, where taped seams or foam may show between the framing, and relies on the roofing permit and the roofer's paperwork. Without either, the answer is unknown. If you are planning a re-roof, this is the moment to ask your roofer which method they use and to keep the documents, because the deck is exposed and SWR is easiest to add and to prove.
- Where we look
- The underside of the deck, plus roofing documents
- Have ready
- The re-roof contract or permit that names the underlayment

Item09
Opening Protection
This item covers every opening in the walls and roof: windows, entry doors, sliding glass doors, skylights, garage doors and glass block. Gable vents and other roof vents are not included. The answer is the weakest protection found on any glazed opening:
- A: products tested for cyclic pressure and a 9-pound large missile (4.5 pounds for skylights), under standards such as Miami-Dade PA 201, 202 and 203, Florida TAS 201, 202 and 203, ASTM E1886 and E1996, or SSTD 12. Garage doors can qualify under ANSI/DASMA 115.
- B: cyclic pressure and a 4 to 8 pound large missile (2 to 4.5 pounds for skylights).
- C: plywood or OSB panels meeting Table 1609.1.2 of the FBC 2007.
- N: protection that appears to meet A or B but cannot be verified, or other coverings that cannot be identified.
- X: one or more glazed openings with no windborne debris protection.
- Z: new in 2026, damaged openings in need of repair or replacement.
Solid entry doors and garage doors without glass get their own sub-level (.1, .2 or .3) next to the main answer. Two rules matter most. One unprotected bathroom window can make the whole house an X, because the weakest opening sets the answer. And the form states that all openings must be in good condition: homes with openings that need replacement do not qualify for wind mitigation rate differentials, regardless of the other features.
Verification is everything here. Impact windows or shutters with no label, permit or product approval to back them up are graded N, even if they are excellent products. Keep the approvals, and leave the labels on the glass.
- Where we look
- Every opening, inside and out, including the garage door
- Have ready
- Window, door and shutter permits, product approvals and access to shutter panels

What happens during the visit, step by step
A wind mitigation inspection is short, but it follows a set order so that nothing on the form is left without proof.
- Booking. We ask for the address, the year the house was built, your insurance deadline and whether you have permits or an old report. You get a firm price before anything is scheduled.
- Arrival and identification. The form ends with a homeowner certification that the inspection was performed and that identification was shown, so you or someone you authorize should be there to let us in and sign.
- The outside. We walk the house, measure the roof perimeter and pitch, photograph the roof covering and look at every window, door, slider, skylight and garage door, including any labels.
- The attic. We check how the deck is nailed, find the weakest roof-to-wall connection and look for signs of a sealed roof deck, photographing each one with a tape measure for scale.
- The paperwork. We match what we saw to permits and product approvals, which often decide items 1, 4 and 9.
- The report. You receive the completed, signed form with its photos, usually the same day. Send it to your insurance agent, who submits it to the insurer.
Most visits take under an hour. Large homes, tight attics, houses with many openings or several roof coverings take longer. If you are also buying the house or your insurer wants more than the wind form, it is easy to combine visits, and our guide to getting a 4-point and wind report in one visit covers the timing.

How to prepare for a wind mitigation inspection
A little preparation is the difference between "verified" and "unknown" on several items. Before the visit:
- Clear the way to the attic hatch, which is often in a closet or the garage ceiling, and move anything stored under it.
- Unlock the garage and any side gates. The garage door is an opening on the form.
- Gather permits for the original construction, the roof, windows, doors, shutters and garage door. Your city or county building department can usually look them up by address.
- Find product approval numbers, either Florida Product Approval or Miami-Dade NOA numbers, on contracts, invoices or the products themselves.
- Leave labels on impact glass and doors. They are often the only proof on site.
- Make shutter panels and their hardware easy to reach so they can be inspected.
- Find your last wind mitigation report, if there is one. It shows what was documented before and what came back unknown.
- Secure pets, especially if the attic access is inside a room they use.

The weakest-link rule, and what "unknown" really means
Because items 5, 6 and 9 ask for the weakest example, a house is credited at the level of its weakest documented feature in each of them. A home with double wraps on the original structure and toe-nailed trusses on a later addition answers toe nails. A home with impact windows everywhere except one small bathroom window answers X. A home with rated windows and an unrated garage door carries that door's sub-level on item 9.
"Unknown" is a different problem. When the inspector cannot see or verify something, because there is no attic access, the paperwork is missing or a product carries no label, the form records it as unknown or unverified. That documents nothing, so your insurer has nothing to credit for that item. Often the fix is paperwork rather than construction: a permit search, a product approval number or an old roofing contract can turn an unknown into a documented answer.
Accuracy cuts both ways. Under Section 627.711, a person who knowingly or through gross negligence provides a false or fraudulent mitigation form can face investigation by the state's insurance fraud investigators, licensing action or prosecution, and using a false form to get a discount you are not entitled to is a first-degree misdemeanor. A good inspector documents exactly what is there and explains what would change an answer, but will never mark a box the evidence does not support.
South Florida: why the same house can answer differently
Where you live changes the form. The Florida Building Code applies the High-Velocity Hurricane Zone only to Miami-Dade and Broward counties. In those two counties, item 2 always answers HVHZ, item 1 offers the SFBC-94 option for homes permitted in the mid-1990s, and item 4 recognizes HVHZ roofing permits from 1994 to 2002. In Palm Beach County, none of those HVHZ options apply, and the region on item 2 depends on the design wind speed at each address.
The coast matters too. Salt air speeds up corrosion on metal straps, clips and shutter hardware, and connectors only count on item 6 when they are free of visible severe corrosion. And much of coastal Broward and Miami-Dade was built before the Florida Building Code existed, so many homes there earn their credits from roof shape, connectors added later and protected openings rather than from the building code item.
If you own a condo, many items on the form describe the building rather than your unit: the roof deck, the roof-to-wall connections and the roof shape belong to the association. Ask your agent which report your insurer wants for your unit's HO-6 policy before you book anything. If you are buying a unit, our guide to milestone inspections and reserve studies covers the building reports worth requesting. For a house, the inspection is the same across the region, but the details differ by city, so each of our local pages explains what is typical there.
Wind mitigation inspections near you
Upgrades that can change your answers
The form documents what exists, so an upgrade only counts once it is finished and documented. After a significant upgrade you need a new inspection, because the old form no longer describes the house and stays valid only if no material changes have been made.
Re-roofing
A re-roof is the one time the roof deck is exposed. It is when a sealed roof deck can be added (item 8), when deck fastening can be brought up to a stronger pattern (item 5) and when a new covering gets its permit and product approval (item 4). Ask your roofer to put the underlayment method and the nailing pattern in writing, and keep the permit.
Roof-to-wall retrofits
Under the 2026 form, purpose-made retrofit connectors can be credited by their documented uplift capacity when installed to the manufacturer's specifications, with site-specific documentation. If you are considering a retrofit, ask the installer for that documentation before the work starts, not after.
Opening protection
Because the weakest opening decides item 9, a partial upgrade may not move the answer at all. Protecting every glazed opening, including small windows, skylights and the garage door, is what changes the result. Keep every product approval and permit.
FORTIFIED certificates
A FORTIFIED Home Roof, Silver or Gold certificate can be used to validate the answers on items 4 through 6 and 8 through 9, and a copy is attached to the form.
Before you spend money, ask your agent how your insurer's credit would change if a specific item improved. Insurers price combinations of answers differently, so a generic savings figure from the internet is a poor way to size an upgrade. The state's My Safe Florida Home program has offered free wind mitigation inspections and grants of up to $10,000 for qualifying improvements, but its funding and application windows come and go, so check mysafeflhome.com for current status and eligibility before planning around it.
Wind mitigation vs. 4-point vs. full home inspection
These three are easy to mix up because insurers and buyers often ask for them in the same week. They answer different questions.
| Wind mitigation | 4-point | Full home inspection | |
|---|---|---|---|
| Purpose | Documents wind-resistant features for windstorm credits | Lets the insurer decide whether to write or renew an older home | Tells a buyer or owner the condition of the whole house |
| What it covers | The nine items on form OIR-B1-1802 | Age, type and condition of the roof, electrical, plumbing and HVAC | Roof, structure, electrical, plumbing, HVAC, attic, interior and appliances |
| Who usually asks | You, to lower the windstorm premium | The insurer, usually for older homes | The buyer, during the inspection period |
| Pass or fail | No | The insurer decides whether it is acceptable | No, it is a report of findings |
| How long it lasts | Up to 5 years if nothing changes | Set by the insurer, often about a year | For the purchase decision |
| Time on site | Usually under an hour | Short, and easy to add to the same visit | Usually 2–4 hours for a single-family home |
Citizens requires a 4-point inspection for homes more than 20 years old, and private carriers set their own limits, often between 20 and 30 years. So a buyer of an older South Florida home often needs all three: the home inspection for the purchase decision, the 4-point so the insurer will write the policy and the wind mitigation report so the windstorm premium reflects how the house is built. If the roof's age is the sticking point with your insurer, a roof inspection documents its condition and remaining life.
How much does a wind mitigation inspection cost?
The price depends on the size and layout of the house, attic access, the number of openings and whether you combine it with a 4-point or a home inspection in the same visit. We do not publish a flat number that might not fit your house. Call (954) 297-0317 with the address and the year it was built, and you will get a firm price before anything is scheduled.
To judge whether the inspection fee is worth it, compare it with the credit your insurer gives for your answers. Your agent can estimate that once they see the report. Because the form can stay valid for up to five years when nothing changes, one inspection may serve several renewals, as long as your insurer accepts it.
Six common misunderstandings
- "My house was built after 2002, so it gets the best answers." Item 1 depends on the permit application date, and the other eight items are documented one by one. A newer house can still have an unknown roof deck or an unprotected opening.
- "I have impact windows, so opening protection is maxed out." Only if every glazed opening is protected and verified. Entry doors, sliders, skylights and the garage door count too.
- "Any shutters count." Shutters with no documentation, or products that cannot be identified, are graded N.
- "The inspector decides my discount." The inspector documents. Your insurer applies credits from its own filed rates.
- "The report is good for five years no matter what." Only while the structure is unchanged and the form is accurate, and only if your insurer accepts it.
- "Wind mitigation and a 4-point are the same thing." One documents wind resistance for credits. The other reports the condition of four systems so the insurer can decide whether to write the policy.
Who can sign a wind mitigation form
Section 627.711(2) of the Florida Statutes lists who can sign the form, and every insurer must accept a form signed by one of them:
- A home inspector licensed under Section 468.8314 who has completed at least three hours of hurricane mitigation training approved by the Construction Industry Licensing Board, including a proficiency exam.
- A building code inspector certified under Section 468.607.
- A general, building or residential contractor licensed under Section 489.111.
- A professional engineer licensed under Section 471.015.
- A professional architect licensed under Section 481.213.
- Any other individual or entity the insurer recognizes as qualified to complete the form.
Except for licensed contractors and engineers, who may send a direct employee, the qualified inspector must perform the inspection personally. It is fair to ask any inspector which category they sign under and for their license number before you book.
The bottom line
A wind mitigation inspection turns the way your house was built into a record your insurer has to consider. It takes about an hour, it cannot be failed, and on the 2026 form it covers nine items, three of which are decided by the weakest example on the house. Preparation matters as much as construction: permits, product approvals and a clear attic hatch are often what separate a documented answer from an unknown one. If you are in Broward, Miami-Dade or Palm Beach County and want to know what your house would show, send us a request or call (954) 297-0317, and you will have a firm price before anything is scheduled. You can also read more about our wind mitigation inspections across South Florida or how an inspection works.
Sources
- Uniform Mitigation Verification Inspection Form, OIR-B1-1802 (Rev. 04/26), Rule 69O-170.0155, Florida Administrative Code
- Section 627.0629, Florida Statutes: residential property insurance rate filings
- Section 627.711, Florida Statutes: notice of premium discounts for hurricane loss mitigation
- Citizens Property Insurance: Uniform Mitigation Verification Inspection Form changes
- ASCE Hazard Tool (design wind speed by address)
- My Safe Florida Home program
Laws, insurer rules and state programs change. This guide reflects these sources as of November 5, 2026.